Delivery time is counted from the date the order is confirming. Mould making 10days, Material preparation about 3 to 5 days, punching 5 days, drilling 3 days, assembling 3 days, polishing 3 days, cleaning and sandblasting 3 days, plating 5-7 days, Epoxy 3 days, QC 1-2 days etc. Then you can count the days by yourselves.